TITLE
Title
Approval of Owner Change Order No. 3 for the Gerald Adams Elementary School Project
end
BACKGROUND INFORMATION
The Substantial Completion Date for Phase I construction was scheduled to be November 21, 2018. Substantial Completion inspection as well as inspections for the Certificate of Occupancy did not take place until November 29, 2018 due to the Thanksgiving Holiday. Phase I was declared Substantially Complete and a Certificate of Occupancy was executed on November 30, 2018. This Change Order is to revise the Phase I Substantial Completion date from November 21, 2018 to November 30, 2018. The Phase II Substantial Completion date remains unchanged.
BUDGET INFORMATION
Item Budgeted? N/A
Total Cost: $0.00
Budget Coding: 0396-7400-630-0311-3296
Change Order Attached? Yes
CONTRACT INFORMATION
Contract with: Ajax Building Corporation
Contract value: $29,831,678.00
Budget coding: 0396-7400-630-0311-3296
Contract Purpose / Description: Approve revision of Phase I Substantial Completion date for the Gerald Adams Elementary School Project
Contract Originator: Douglas Pryor, 53465, Planning/Construction
Board Meeting Date: February 12, 2019
RECOMMENDATION
Recommendation
Approval of Owner Change Order No. 3 for the Gerald Adams Elementary School Project