Title: Approve GMP Deduct Change Order No. #7 to Biltmore Construction Co., Inc. for the Plantation Key School Project
Attachments: 1. PKS Change Order #7, 2. PKS Settlement Agreement Fully Executed
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TITLE

Title

Approve GMP Deduct Change Order No. #7 to Biltmore Construction Co., Inc. for the Plantation Key School Project

 

end

 

BACKGROUND INFORMATION

On March 20, 2018 the School Board of Monroe County approved Deduct Change Order No. #3 to GMP Amendment No. #2 and Amendment No. #3 to Biltmore Construction Co., Inc. to modify the agreement by change order to deduct costs for Owner Direct Purchases. The attached Change Order #7, deducts Project Tax Savings from the Owner Direct Purchase Program in the amount of $355,353.56. Change Order #7 also includes a reimbursement of $16,012.50 for additional services paid to Zyscovich Architects as approved by the School Board on December 17, 2019. The final GMP will be decreased by a total amount of $371,366.06.

 

BUDGET INFORMATION

Item Budgeted? N/A

Total Cost: Deduct <$371,366.06>

Budget Coding: 0396-7400-0630-0321-3292

Requisition Attached? N/A

 

CONTRACT INFORMATION

Contract with: Biltmore Construction Company, Inc.

Contract value: Revised Final GMP $28,028,518.64

Budget coding: 0396-7400-0630-0321-3292

 

Contract Purpose / Description: To approve GMP Deduct Change Order No. #7 to Biltmore Construction Co., Inc. for the Plantation Key School Project

 

Contract Originator: Douglas Pryor, 53465, Planning/Construction

 

Board Meeting Date: January 21, 2020

 

RECOMMENDATION

Recommendation

Approve GMP Deduct Change Order No. #7 to Biltmore Construction Co., Inc. for the Plantation Key School Project