Title: Award ITB 2020016 Key West High School New Corridor Contract to Design Center, Inc.
Attachments: 1. KWHS A101 Completed with LD, 2. AIA 101 page 10, 3. A201-2017_2010494092_03112020031632_a333d4b5-9859-40c9-9829-aa88e04fea6c, 4. Key_West_Highschool_New_Corridor_Project_Bid_Packet_Complete, 5. Certificate of Auto Liability Insurance, 6. Certificate of GL Insurance, 7. Certificate of WC Liability Insurance
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TITLE

Title

Award ITB 2020016 Key West High School New Corridor Contract to Design Center, Inc.

 

end

 

BACKGROUND INFORMATION

In accordance with Florida requirements, ITB 2020016 for Key West High School New Corridor went out to the public on January 17, 2020 via DemandStar and the District's website. There were 647 suppliers notified and 16 planholders. Three responses to the advertised ITB were received. The bid proposals were reviewed by a selection committee on March 5, 2020. Selection was based on the best priced proposal that met the contract award requirements. The contractor selected for this work was Design Center, Inc.

 

BUDGET INFORMATION

Item Budgeted? Yes

Total Cost: $259,924.60

Budget Coding: 0370-7400-682-0101-3288

ITB Attached? Yes

 

CONTRACT INFORMATION

Contract with: Design Center, Inc.

Contract value: $ 259,924.60

Budget coding: 0370-7400-682-0101-3288

 

Contract Purpose / Description: Key West High School New Corridor Project

 

Contract Originator: Michael Skrodinsky, 53405, Maintenance

 

Board Meeting Date:  March 31, 2020

 

RECOMMENDATION

Recommendation

Recommend Award of ITB 2020016 Key West High School New Corridor Contract to Design Center, Inc.